Installation example No.21
Connection of insulated conductors ABC in the range
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 3417070 | MJPT 70N | FID-N jointing sleeves for conductors-zero conductor | 4 |
Installation example No.20
Connection of insulated conductors ABC in the range
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 3415454 | MJPT 54 N | FID jointing sleeves for phase conductors | 1 | |
2 | 3402525 | MJPT 25 | FID jointing sleeves for phase conductors | 1 | |
3 | 3405050 | MJPT 50 | FID jointing sleeves for phase conductors | 3 | |
4 | 1710189 | FKV 180/9 | Cable tie | 2 |
Installation example No.19
Connection on the building with entrance through the measuring-distribution enclosure- electric meter
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 3810008 | AC 25 | Steel wall bracket for household connection of ABC | 1 | |
2 | 3813025 | PA/PS 416/35 | Tension support clamp for LV ABC | 2 | |
3 | 5082030 | MRO 1 | Measuring-distribution polyester enclosure 320x665x235 | 1 | |
4 | 1714060 | FZN 60 | Wall bearer with binding thread | Distance gap between vulture and the wail of the building must be at least 0.06M | 3 |
Installation example No.18
Angular carrying support of the main ABC line and separating for household connection
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 4710080 | F 207 | Stainless steel band | (0.19×0.7x5000M) | 4 meters |
2 | 4710320 | A 20 | Clips | 19 mm | 4 |
3 | 3810021 | ES 1500 | Al bracket with clamp for carrying support up to 25-95mm² conductor | 1 | |
4 | 3804350 | PC 4-150 | Insulated waterproof connecting clamp FIDOS 4-35/6-150 | 2 | |
5 | 1710189 | FKV 180/9 | Cable tie | 3 | |
6 | 3810013 | CA 1500/2000 | Al bracket | 1 | |
7 | 3811625 | PA 25 | Tension support clamp for household connection | 1 |
Installation example No.17
Tension binding of ABC to household connection, when the distance between the posts is greater than standard
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 3100074 | PSK 7 | Hock PSK 7 ∅ 16 | 1 | |
2 | 3813025 | PA/PS 416/35 | Tension support clamp for LV ABC | 2 |
Installation example No.16
Tension binding of ABC to household connection, when the distance between the posts is greater than standard.
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 4710080 | F 207 | Stainless steel band | (0.19×0.8x5000M) | 2 meters |
2 | 4710320 | A 20 | Clips | 19 mm | 2 |
3 | 3810013 | CA 1500/2000 | Al bracket | 1 | |
4 | 3811625 | PA 25 | Tension support clamp for household connection | 2 | |
5 | 1710189 | FKV 180/9 | Cable tie | 2 |
Installation example No.15
Separation of ABC for household connection from non-insulated overhead line
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 3811625 | PA 25 | Tension supporting clamp for household connection | 1 | |
2 | 3801525 | N.F 2.5-150 | Insulated waterproof clamp for transfering from non-insulated conductor to ABC NF 2.5-150 | 2 |
Installation example No.14
Transfering from non-insulated overhead line to ABC
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 4710080 | F 207 | Stainless steel band | (0.19×0.7x5000M) | 2 meters |
2 | 4710320 | A 20 | Clips | 19mm | 2 |
3 | 3810013 | CA 1500/2000 | Al bracket | 1 | |
4 | 3812079 | PA 1500 | Tension support clamp for ABC 54-71.5 mm² | 1 | |
5 | 1710189 | FKV 180/9 | Cable tie | 3 | |
6 | 3802525 | NF 25-150 | Insulated waterproof clamp for trasfering from non-insulated conductor to ABC NF 25-150 | 4 | |
7 | 3801525 | NF 2.5-150 | Insulated waterproof clamp for trasfering from non-insulated conductor to ABC NF 2.5-150 | 1 |
Installation example No.13
Example of connecting the street light on ABC
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quantity | pcs. |
1 | 3100074 | PSK 7 | Hook PSK ∅16 | 1 | |
2 | 3810015 | RA 25 | Angular carrying support clamp | 1 | |
3 | 1710189 | FKV 180/9 | Cable tie | 1 | |
4 | 3801595 | PC 10-95 | Insulated waterproof connecting clamp FIDOS 105-10/16-95 | 2 | |
5 | LED light | 30W. 60W. 90W | 1 | ||
6 | 4710080 | F 207 | Stainless steel band | (0.19×0.7x5000M) | 2 meters |
7 | 4710320 | A 20 | Clips | 19mm | 2 |
Installation example No.12
Example of connecting the street light on ABC
Material list necessary for installation :
No | Code Marking | Products Name | Note | Quentity | pcs. |
1 | 4710080 | F 207 | Stainless steel band | (0.19×0.7x65000M) | 4 meters |
2 | 4710320 | A 20 | Clips | 19mm | 4 |
3 | LED light | 30W,60W,90W | 1 | ||
4 | 3804350 | PC 4-150 | Insulated waterproof connecting clamp FIDOS 4-35/6-150 | 2 | |
5 | 1710189 | FKV 180-9 | Cable tie | 4 | |
6 | 3810021 | ES 1500 | Al bracket with carrying support clamp up to 25-95mm² conductor | 1 |